In a FOI request, B&H were asked about the timeline of delivery of their current road schemes, they are:
Valley Gardens:
- Technical Design from January 2021 to January 2022
- Construction from August 2022 to March 2024
- Post Construction monitoring from 2024 till 2027
Active Travel Fund 2 Schemes:
A259 – Phase 2 (temporary extension)
- January-February 2022 – Assessment & design work
- March 2022 – ETS committee
- May-June 2022 – Construction
A23 – Phase 1 (permanent cycle tracks from A27 to Stanford Avenue)
- Further Consultation Q4 2021/ Q1 2022
- March 2022 – ETS committee
- Further design & construction dependant on outcome
Western Road
- Detailed design – October/November 2021
- Contractor procurement – November 2021/January 2022
- Construction – March 2022 to March 2024
Active Travel Fund 3 Schemes:
Estimated construction/completion dates
- Old town – March 2022 to March 2023
- Marine Parade – July 2022 to March 2023
- A23 phase 2 (Stanford Avenue to Valley Gardens) feasibility study – October 2022 to March 2023
- A23 north* – October 2022 to March 2023
- New Church Road / Church Road feasibility study – October 2022 to March 2023
- Lewes Road feasibility study – October 2022 to March 2023
*Not sure what is meant by A23 north. Could mean north of A27 (although unlikely), or could mean Stanford Avenue or maybe other parts of phase 1.