In a FOI request, B&H were asked about the timeline of delivery of their current road schemes, they are:

Valley Gardens:

  • Technical Design from January 2021 to January 2022
  • Construction from August 2022 to March 2024
  • Post Construction monitoring from 2024 till 2027

Active Travel Fund 2 Schemes:

A259 – Phase 2 (temporary extension)

  • January-February 2022 – Assessment & design work
  • March 2022 – ETS committee
  • May-June 2022 – Construction

A23 – Phase 1 (permanent cycle tracks from A27 to Stanford Avenue)

  • Further Consultation Q4 2021/ Q1 2022
  • March 2022 – ETS committee
  • Further design & construction dependant on outcome

Western Road

  • Detailed design – October/November 2021
  • Contractor procurement – November 2021/January 2022
  • Construction – March 2022 to March 2024

Active Travel Fund 3 Schemes:

Estimated construction/completion dates

  • Old town – March 2022 to March 2023
  • Marine Parade – July 2022 to March 2023
  • A23 phase 2 (Stanford Avenue to Valley Gardens) feasibility study – October 2022 to March 2023
  • A23 north* – October 2022 to March 2023
  • New Church Road / Church Road feasibility study – October 2022 to March 2023
  • Lewes Road feasibility study – October 2022 to March 2023

*Not sure what is meant by A23 north. Could mean north of A27 (although unlikely), or could mean Stanford Avenue or maybe other parts of phase 1.